Project

Remodelling of Murtala Mohammed Square

Project Details

Murtala Square was developed to serve as a sporting and recreational centre for residents of the State and visitors alike.

Over time, the facility has become a complex which houses a standard Olympic-size swimming pool, diving pool, two hockey pitches, volleyball courts, handball courts, basketball courts, cricket pitch, traditional sports venue, tennis courts, football pitch, pavilions, taekwondo centre, race course, and an auditorium for multipurpose sports and events.

However, the facility is in deplorable condition and can no longer compete with other sporting and recreation facility around the world.

KMDMC is remodelling the entire facility to a world-class sporting centre with additional facilities for hospitality. The facility will be concessioned to a competent manager at completion to operate and manage.

The new development will include conversion of Yar'adua Indoor Sports Hall to a Conference Hall, remodelling of Olympic Size Swimming Pool, Diving Pool and Diving Platform, construction of Fence, Gate and Gate House, renovation of Central Pavilion & Hockey Pitch Grandstand, construction of a new Clubhouse, conversion of Pavilion to Boutique Hotel and Tech Hub, Natural Grass Pitches & General Landscraping, and other infrastructure.

Subproject Highlights

  • Subproject A

    Title

    Conversion of Yar'adua Indoor Sports Hall to a Conference Hall

    Award Date

    24th December 2019

    Total Contract Sum

    N539 million

    Amount Paid

    N377 million

    Project Duration

    3 Months

    Consultants

    Sal Consults Limited

    Contractor

    Golden Shell Limited

    Location

    Race Course, Kaduna

  • Subproject B

    Title

    Remodelling of Olympic Size Swimming Pool, Diving Pool and Diving Platform

    Award Date

    13th January 2020

    Total Contract Sum

    N80 million

    Amount Paid

    N16 million

    Project Duration

    2 Months

    Consultants

    Sal Consults Limited

    Contractor

    Panobez Limited

    Location

    Race Course, Kaduna

  • Subproject C

    Title

    Construction of Fence, Gate and Gate House

    Award Date

    2nd January 2020

    Total Contract Sum

    N92 million

    Amount Paid

    N18 million

    Project Duration

    6 Months

    Consultants

    Sal Consults Limited

    Contractor

    New Complex Nigeria Limited

    Location

    Race Course, Kaduna

  • Subproject D

    Title

    Renovation of Central Pavilion & Hockey Pitch Grandstand

    Award Date

    20th January 2020

    Total Contract Sum

    N128 million

    Amount Paid

    N25 million

    Project Duration

    4 Months

    Consultants

    Sal Consults Limited

    Contractor

    Eliaj Construction Limited

    Location

    Race Course, Kaduna

  • Subproject E

    Title

    Construction of New Clubhouse

    Award Date

    13th January 2020

    Total Contract Sum

    N377 million

    Amount Paid

    N75 million

    Project Duration

    7 Months

    Consultants

    Sal Consults Limited

    Contractor

    Kestrel Global Investments Limited

    Location

    Race Course, Kaduna

  • Subproject F

    Title

    Conversion of Pavilion to Boutique Hotel and Tech Hub

    Award Date

    13th January 2020

    Total Contract Sum

    N256 million

    Amount Paid

    N51 million

    Project Duration

    7 Months

    Consultants

    Sal Consults Limited

    Contractor

    Bricks International Concepts Limited

    Location

    Race Course, Kaduna

  • Subproject G

    Title

    Infrastructure

    Award Date

    2nd January 2020

    Total Contract Sum

    N569 million

    Amount Paid

    N113 million

    Project Duration

    6 Months

    Consultants

    Sal Consults Limited

    Contractor

    Bricks International Concepts Limited

    Location

    Race Course, Kaduna

  • Subproject H

    Title

    Natural Grass Pitches & General Landscraping

    Award Date

    13th January 2020

    Total Contract Sum

    N232 million

    Amount Paid

    N46 million

    Project Duration

    3 Months

    Consultants

    Sal Consults Limited

    Contractor

    Reform Construction Company Limited

    Location

    Race Course, Kaduna